EXECUTION PHASE
WORK PREPARATION:
- Determining the final hood design and releasing it for production. Solinso provides feedback to the contractor before the cutting drawing becomes final. This involves looking at counter batten height, batten spacing/batten distribution, ventilation and any roof foil.
- Managing electrical preparations in the home. This involves laying empty pipes between the meter cupboard and the location of the inverter. But also the route of the string cabling from the roof surface to the location of the inverter.
- Points of attention for an electrician. The electrician installs the earth leakage circuit breaker in the meter cupboard, installs the cabling up to a maintenance switch (including protective earth) at the location of the inverter and provides the group in the distribution box with the correct stickers. The electrician must also include the provisions for an Ethernet connection, which provides data access to the inverter.
- An inverter requires physical space of, for example, (hxw) 100cm x 75cm with an maintenance switch mounted underneath. This space must be fixed.
INSTALLATION:
- It is desirable to place the roof tiles and solar roof tiles together on the roof because of the mutual dependency on size. If necessary, Mystiek can be laid prior to the roof tiles, provided that Mystiek is laid out in the correct roof tile size. The roofer must/can then connect the roof tiles seamlessly to Mystiek.
- After installing Mystiek, it is important to test the operation of the installation. After all, in new construction the inverter is usually installed just before completion, and that can be months later. If an error is detected at that time, the roof is no longer accessible.
IN OPERATION:
- During roof renovations, the Mystiek installation can be carried out parallel to the installation of the inverter. Reading the inverter via the internet can usually also be adjusted directly.
- In new construction, this is only possible after the grid operator has installed electricity to the home. Shortly afterwards, the inverter is installed and the solar roof tiles can actually start supplying power.
- The new-build home is often only provided with an internet connection months after completion. From that moment on, it will also be possible to read the energy production of the solar panels via an App. You can take care of this yourself or have it done by the specialist who installed the inverter.